Production continues to increase at a mine development near Snow Lake.

VMS Ventures reports considerable progress was made in November at the Reed copper mine which is owned 30 percent by VMS and 70 percent by Hudbay who is the operator.

             

During the month they surpassed two thousand meters of total underground project and pre-production development, completed 627 days without a lost time accident, completed 85 meter ore development from two zones with production of over 13 thousand tonnes of ore, completed two ventilation raises, commissioned the main fresh air ventilation fan on the 50 meter level and remain on budget and on schedule.

             

The focus this month is on safety and continued ramp development down to the 135 meter level and pre-production development at the 110 meter level of the mine.  The project is expected to reach commercial production by the second quarter of next year.

 

Frontline Sport & Leisure - U-Pick/Opinion Poll

Frontline Sport & Leisure U-Pick Song of the Day -Songs About Friendship

Your Calendar

March

S M T W T F S
          1 2
3 4 5 6 7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28 29 30
31            

Weather